Dependencies are a useful tool in Aspenify that allow you to set the order in which activities should be completed in a Playbook that will then drive that order for any Initiatives created.
You can order the activities by making an activity dependent on any activity that preceded it, this will ensure that the preceding activity is completed before the next can be started.
The set of dependencies that create the longest timeline in a Playbook determine it's critical path timeline, therefore if any activity in that critical path is delayed, the completion date of the overall initiative is delayed*.
See dependencies and duration user guide for additional information.
If this does not solve your issue, or you need additional customer support, you may contact us via one of our direct support options located here.
* There are project management techniques that can be used to get a project back on the critical path.